Front Gate Refresh Project

Updates on Front Gate Refresh and Construction
Front Gate Dec 2023 - Before Photo: Sydney Walsh
Major Projects

Front Gate Refresh Project

Updates on Front Gate Refresh and Construction

Front Gate Under Construction

Exciting news! After receiving funding from City Council District 3 and San Antonio Water System, the front gate renovation project is finally underway. There will be changes to how you enter and exit the property during this time.

  • The main entrance will be closed beginning 6/25/2024 until the project is complete, with completion scheduled for October 2024.
  • An alternative and temporary entrance is provided just past the current entrance, starting 6/25/2024. This will serve as both the entry and exit to the property.
  • The temporary entrance will be the main access point for visitors, staff, and construction contractors – please be aware of construction equipment and vehicles when entering and exiting the property.
  • Summer hours are 7:00am – 1:00pm, with last entry at 12:00pm. The gates will be manually closed at 1:00pm and no exit afterward – you will be locked in!